446f0f04-8528-ec48-1757-94945665eadf

Living Choice Parkwood – Construction Progress Update

We’re excited to share a construction update for Living Choice Parkwood.

Project Update:

Building 2 – Lexington

  • Podium – Complete clean and commissioning of services
  • L1 – L3 – Complete final clean and commissioning of services
  • L4 – L5 – Final fitments and paint
  • Façade – Complete from level 1 above
  • Balustrade – Complete from level 1 above
  • External tiling to balconies – complete from level 1 above
  • Render/Paint – Complete from level 1 above
  • Undertaking podium works, planters, concrete works and landscaping

 

Building 4 – Lakeshore

  • Podium – Framing 90% complete, services rough in (first fix) 80%
  • L1 – Framing 90%, Windows 80%
  • L2 – Framing 20% Windows 30%
  • L4 – Slab to be poured next week

 

Other Areas

  • Welcome Centre – Completed external works and commissioning
  • Roundabout – Concrete works complete, undertaking kerbs, lights and landscaping
  • Zone 6 – podium formwork complete, reinforcing and in slab services underway
  • Buggy path- concrete works 50% complete

 

Click here to watch the video

 

We currently have three stunning display apartments open – The Peacock, The Thornbill and The Hummingbird. Book a private tour today or join our open day on Tuesday 3rd of February.

To find out more call Amy Roach: 1300 421 414