Building 2 – Lexington
- Podium – Complete clean and commissioning of services
- L1 – L3 – Complete final clean and commissioning of services
- L4 – L5 – Final fitments and paint
- Façade – Complete from level 1 above
- Balustrade – Complete from level 1 above
- External tiling to balconies – complete from level 1 above
- Render/Paint – Complete from level 1 above
- Undertaking podium works, planters, concrete works and landscaping
Building 4 – Lakeshore
- Podium – Framing 90% complete, services rough in (first fix) 80%
- L1 – Framing 90%, Windows 80%
- L2 – Framing 20% Windows 30%
- L4 – Slab to be poured next week
Other Areas
- Welcome Centre – Completed external works and commissioning
- Roundabout – Concrete works complete, undertaking kerbs, lights and landscaping
- Zone 6 – podium formwork complete, reinforcing and in slab services underway
- Buggy path- concrete works 50% complete