Living Choice Galston Construction Update

Good weather and great progress have created much interest these past few weeks at Living Choice Galston.

Since the last construction update, we now have a fully operational sales office, open from 10-4pm Wednesday to Saturday.

Site Manager, Scott Henry, said he’s happy with the progress made in October/November, including:

  • The stormwater detention tank is 80% completed.
  • Backfilling of dam is very close to completion.
  • The construction of retaining walls is continuing for building pads.
  • Villa pads 36 - 40 continue to be trimmed and handed over.
  • Installation of service mains for the village is in progress. (fire, water, stormwater, sewer, electrical and communications)
  • Villa slabs 30 – 35 have been poured.
  • We are continuing to pour villa slabs with villas 27 – 29 due next week.
  • Our first road pour.
  • Onsite sewer pump station is completed pending electronics.
  • Turf has been installed in the stormwater swales.
  • Villa frame installation is 90% complete on villas 34 and 35.
  • We have frames and trusses on site for villas 30 - 33.
  • Villa roof installation has started.

The sales office will be open Wednesday to Saturday from 10am to 4pm. To make an appointment, please phone 1800 797 333 or email sales@livingchoice.com.au